Excavation SWMS template Australia
A trench or shaft deeper than 1.5 metres is high-risk construction work. Ground collapse and buried services kill people on suburban blocks, not just civil jobs. If the hole stays under 1.5 m and no other HRCW applies, you may be on a JSA — this page is for when it doesn’t.
Trench deeper than 1.5 m is HRCW
HRCW: trench or shaft with excavated depth greater than 1.5 m. Collapse, engulfment, incoming services, and sometimes a confined-space overlay if the atmosphere turns. If it becomes a pit you enter with a restricted opening, also see confined space.
Filled example: sewer connection trench, Springfield Lakes QLD
New dwelling. Excavator cuts a connection trench to the council sewer — deeper than 1.5 m at the tie-in. Sandy ground, a water main marked on the BYDA plan, and a person in the hole to make the joint.
Example layout. A person in a trench deeper than 1.5 m needs shoring or a batter that actually works in that ground — not a hope. Unexpected ACM in old pipe: asbestos SWMS.
| Step | Hazards | Controls | 5×5 risk |
|---|---|---|---|
1. BYDA, locate services, and set the exclusion around the excavator Responsible: Supervisor |
|
| InitialL4×C5 = 20 Critical ResidualL2×C5 = 10 High |
2. Excavate, batter or shore once the depth hits 1.5 m Responsible: Plant operator / leading hand |
|
| InitialL4×C5 = 20 Critical ResidualL2×C5 = 10 High |
3. Worker in the trench to lay pipe and make the sewer joint Responsible: Drainer |
|
| InitialL3×C5 = 15 High ResidualL2×C5 = 10 High |
4. Backfill, compact, remove shoring Responsible: Leading hand |
|
| InitialL3×C5 = 15 High ResidualL2×C5 = 10 High |
Frequently asked questions
When do I need an excavation SWMS template?
When the work is in a trench or shaft with an excavated depth greater than 1.5 metres. That is HRCW. Shoring, battering, services and a rescue plan are part of the SWMS, not a toolbox chat.
Is the excavation SWMS free?
Creating an account is free and needs no card; creating and editing your own site-specific draft is free too. The $20/month subscription is only needed to download the PDF. This Springfield Lakes sewer trench is an example layout — sand in QLD is not clay in VIC.
SWMS or JSA for a shallow service trench?
Under 1.5 m, no collapse risk of that kind, no other HRCW: a JSA may be enough. The moment you go deeper, or you put a person in the hole, use this SWMS. Don’t “average” the depth on paper.
Valid in NSW, VIC, QLD and WA?
Yes — WHS Act/Regulation, or Victoria’s OHS Act 2004 and OHS Regulations 2017. Dial Before You Dig / Before You Dig Australia still applies everywhere.
Check the official guidance
A SWMS sets out the high-risk construction activities, their hazards and the controls to use. Prepare it before the work starts, adapt it to the site and review it when the work or controls change. Consult the people doing the work. An AI draft or example needs review before use.
- Safe Work Australia: preparing and using a SWMS
- WorkSafe Victoria: SWMS duties under Victorian OHS rules
Model WHS guidance and Victorian requirements differ. Check the rules that apply to your workplace.