• SWMS template · load-bearing demolition
Demolition SWMS template Australia
Knocking out a load-bearing wall is high-risk construction work whether the site is a tower or a brick shop in Newtown. Temporary support, falling masonry, and an asbestos check before strip-out are the job. A fit-out JSA does not cover the wall.
Load-bearing demolition is HRCW
HRCW: demolition of a load-bearing element, or an element related to structural integrity. Temporary propping is often a second category (temporary load-bearing support). One SWMS can cover both if it is honest about the sequence.
Asbestos: check the register and sample before strip-out. If it is ACM, this is no longer “just demo” — switch to the asbestos SWMS and a licensed removalist where the law requires it.
Filled example: load-bearing wall, Newtown NSW
Brick shop conversion. Knock through a load-bearing internal wall after needle beams and props. Occupied florist next door. Not a full building pull-down, not a ground-floor plaster soft strip.
Example layout. Asbestos check before the first bar. If ACM is confirmed, stop and use the asbestos SWMS — don’t keep this sequence going.
| Step | Hazards | Controls | 5×5 risk |
|---|---|---|---|
1. Read the asbestos register, sample if needed, and isolate the bay Responsible: Supervisor |
|
| InitialL3×C5 = 15 High ResidualL2×C5 = 10 High |
2. Install needle beams and props to the engineer’s sketch Responsible: Leading hand |
|
| InitialL3×C5 = 15 High ResidualL2×C5 = 10 High |
3. Cut and drop the masonry in controlled bites Responsible: Demolition worker |
|
| InitialL4×C5 = 20 Critical ResidualL2×C5 = 10 High |
4. Clean out, leave props until the lintel is in, then strip temporary works Responsible: Supervisor |
|
| InitialL3×C5 = 15 High ResidualL2×C5 = 10 High |
Frequently asked questions
When is a demolition SWMS template required?
When you demolish an element of a structure that is load-bearing or otherwise related to its physical integrity. That is HRCW. Soft strip of non-structural plaster on a ground floor might be a JSA — only if no ACM, no structural element, no other HRCW.
Is there a free demolition SWMS?
Creating an account is free and needs no card; creating and editing your own site-specific draft is free too. The $20/month subscription is only needed to download the PDF. Don’t take this Newtown shop example to a warehouse mezzanine and sign it.
What if we find asbestos during demolition?
Stop, isolate, don’t keep swinging. Planned ACM removal is a different SWMS (and usually a licensed job). Use the asbestos SWMS page, not this demolition sequence.
NSW, VIC, QLD, WA — same demolition SWMS?
The HRCW trigger is the same idea. Citations: WHS Act/Regulation, or Victoria’s OHS Act 2004 and OHS Regulations 2017. Local demolition licensing and notification rules still apply.
Check the official guidance
A SWMS sets out the high-risk construction activities, their hazards and the controls to use. Prepare it before the work starts, adapt it to the site and review it when the work or controls change. Consult the people doing the work. An AI draft or example needs review before use.
- Safe Work Australia: preparing and using a SWMS
- WorkSafe Victoria: SWMS duties under Victorian OHS rules
Model WHS guidance and Victorian requirements differ. Check the rules that apply to your workplace.