• SWMS template · mobile crane lifting operations
Crane and lifting SWMS template Australia
A crane lift is the one job where everyone on site stops to watch, and the one where the SWMS most often just says 'follow the lift plan'. The lift plan is one control. The SWMS has to say how the ground was checked, where the exclusion zone is, who directs, and what happens when the wind picks up. This page shows what a crane and lifting SWMS should contain.
When a crane and lifting SWMS is the right document
HRCW categories: work in an area with movement of powered mobile plant; risk of a fall greater than 2 m for anyone receiving a load; work on or near energised electrical services when the boom can reach a line; tilt-up or precast concrete; and work on or adjacent to a road when the crane sits on the street. Model WHS regulation 291 and Schedule 3.
- Mobile slewing cranes and Frannas on construction sites.
- Crane trucks (vehicle loading cranes) delivering trusses, frames, glass or plant.
- Tower crane interfaces for trades receiving loads on a deck.
- Lifts over public footpaths or roads: add a traffic guidance scheme.
The SWMS must describe the actual lift: load weights, radius, ground conditions, the exclusion zone and the sequence. A generic 'crane operations' SWMS with no numbers will not survive an inspector's visit. Full list of categories on the HRCW checklist.
Filled example: roof truss lift onto a two-storey house, Ballarat VIC
Twenty-eight prefabricated trusses, heaviest 380 kg, lifted in bundles with a 25 t slewing crane parked on the street. Top plate at 6.2 m. Overhead service line to the neighbour's house, 8 m from the crane. Victoria, so the document cites the OHS Act 2004 and OHS Regulations 2017 and Energy Safe Victoria's No Go Zone rules. The carpenters receiving trusses are on the carpentry SWMS; this document is the lift.
Example layout — not a copy-paste legal document. Residual risk while a bundle is suspended stays High. Unloading truss bundles at ground level with a forklift and no crane is a different document.
| Step | Hazards | Controls | 5×5 risk |
|---|---|---|---|
1. Verify the lift plan, position the crane on the street and set outriggers Responsible: Crane operator (C2) / lift supervisor |
|
| InitialL3×C5 = 15 High ResidualL2×C5 = 10 High |
2. Sling truss bundles at the delivery truck Responsible: Dogger (DG) |
|
| InitialL3×C5 = 15 High ResidualL2×C4 = 8 High |
3. Lift bundles over the frame and land on the top plate Responsible: Dogger / carpenters receiving |
|
| InitialL4×C5 = 20 Critical ResidualL2×C5 = 10 High |
4. Stow the crane, reopen the street and record the lifts Responsible: Lift supervisor |
|
| InitialL3×C4 = 12 High ResidualL1×C4 = 4 Medium |
Related documents on the same lift
The steel or trusses being received are on the steel erection SWMS and carpentry SWMS pages. A crane parked on a live road needs the traffic control SWMS as well. Generate one document per crew and reference the lift plan in each.
Frequently asked questions
Is a crane lift high-risk construction work?
A mobile crane is powered mobile plant, so work in the area where it moves is HRCW. Slinging or landing loads over 2 m up is a fall risk. A boom within reach of overhead lines is work near energised electrical services. Lifting tilt-up or precast panels is named outright. Almost every construction crane lift needs a SWMS.
Which high-risk work licences apply?
Slewing mobile cranes: C2 (up to 20 t), C6 (up to 60 t), C1 (up to 100 t) or C0 (open). Non-slewing cranes such as a Franna over 3 t: CN. Anyone slinging the load or directing the crane needs a dogging (DG) licence. Complex lifts involving rigging equipment beyond standard slinging need a rigger (RB, RI or RA). Vehicle loading cranes over 10 metre-tonnes: CV. Name them in the SWMS.
Does the crane hire company's SWMS cover my crew?
Their SWMS covers their operator and their crane. Your SWMS covers your people working around it: where they stand, who tags the load, who receives it at height, and how the drop zone is kept clear. Both should reference the same lift plan.
How close can a crane work to power lines?
Each state sets no-go zones and approach distances by voltage and whether a spotter is used. In NSW, for example, plant must stay 3 m from lines up to 132 kV unless the network operator agrees otherwise; Victoria uses its No Go Zone framework with 6.4 m for uninsulated lines without a spotter. The SWMS has to state the distance for this site and this line, and the generator inserts the state rule.
Is a crane SWMS valid in NSW, VIC, QLD and WA?
The generator cites the WHS Act and Regulations for NSW, QLD, WA and the other model-WHS states, and the OHS Act 2004 and OHS Regulations 2017 for Victoria. Licence classes are national.